24/02/2015 Network control centre of Power Distribution Zone "Sofievsky" and Power Distribution Zone "Krivoy Rog" of PJSC "DTEK Dneproenergo" put into commercial operation. During the implementation of the projects, 31 substations of different voltage classes were RTU installed.
2021 Under the subcontract, our company performed the supply of equipment and commissioning works of the RZA, ACS TP of the substation and ASKOE, as well as a complex of works on the commissioning of the substation 330 kV "Tyligul" substation for the connection of the wind power station "DTEK Tyligulska wind power station"