and secondary wiring VT-110 kV at the SS "Khmelnitskaya" SE "NPC "UKRENERGO"
30/04/2015 At the SE "NPC "Ukrenergo" was completed work on the modernization of the bus differential protection 110 kV and secondary wiring VT-110 kV at the substation "Khmelnitskaya" with the replacement of the Relay Protection and Automatic Equipment and the implementation of progressive technologies based on microprocessing terminals. The works were performed in a short time on the operating equipment without technological disturbances and without consumer constraint.
2021 Under the subcontract, our company performed the supply of equipment and commissioning works of the RZA, ACS TP of the substation and ASKOE, as well as a complex of works on the commissioning of the substation 330 kV "Tyligul" substation for the connection of the wind power station "DTEK Tyligulska wind power station"