10/02/2015 The design of relay protection and automation, substation control system, auxiliary service panels, operative current cabinet and an automation accounting system at the SS 110/35/10 kV "Slavutych" were completed.
2021 Under the subcontract, our company performed the supply of equipment and commissioning works of the RZA, ACS TP of the substation and ASKOE, as well as a complex of works on the commissioning of the substation 330 kV "Tyligul" substation for the connection of the wind power station "DTEK Tyligulska wind power station"