07/07/2014 The design of relay protection and automation and the creation of substation control system "MSDS-1" 150/6 kV of Ferrexpo "Poltava Mining" was completed. At the moment, the process of setting up the Relay Protection and Automatic Equipment and the SCS "MSDS-1" is underway.
2021 Under the subcontract, our company performed the supply of equipment and commissioning works of the RZA, ACS TP of the substation and ASKOE, as well as a complex of works on the commissioning of the substation 330 kV "Tyligul" substation for the connection of the wind power station "DTEK Tyligulska wind power station"