2020 The specialists of our company performed a full range of works (design, supply of equipment, construction, installation and commissioning works) on the reconstruction of the 150/35/6 kV Lisky substation of JSC Mykolayivoblenergo
Tiligulska wind power plant
2021 Under the subcontract, our company performed the supply of equipment and commissioning works of the RZA, ACS TP of the substation and ASKOE, as well as a complex of works on the commissioning of the substation 330 kV "Tyligul" substation for the connection of the wind power station "DTEK Tyligulska wind power station"